+8618534658602 Installation Precautions for Gully Grating Frame Fixing and Road Level Coordination
In the installation of gully gratings, the fixing method of the frame and its coordination with the road surface level directly determine the operational stability and traffic safety of the grating. The following key technical points are provided for the reference of on-site construction and supervision personnel.
I. Key Points for Frame Fixing
The foundation support must be solid and level. The bottom of the frame must be placed on a compacted, level base layer. Placing the frame directly on loose backfill or uncompacted cushion layers is prohibited. It is recommended to cast a concrete foundation support with a strength grade not lower than C20, with surface flatness deviation controlled within ±3mm. The support width should extend at least 100mm beyond the outer edge of the frame.
The frame must be reliably anchored to the foundation. Relying solely on the frame's self-weight or surrounding filler is prone to displacement under vehicle impact. Embedded anchors or expansion bolts should be installed around the frame, with anchor points spaced no more than 500mm apart, and fixed points must be provided at all four corners. For heavy-duty gratings, through-anchors or welded fixing methods should be adopted.
The frame levelness must be strictly controlled. A tilted frame will cause uneven contact between the grating and the frame, leading to abnormal noise, warping, or even dislodgement. During installation, a level should be used to calibrate each side, with bidirectional levelness deviation not exceeding 2mm/m. Adjustment shims should be made of stainless steel or galvanized material to prevent loosening due to corrosion.
II. Key Points for Road Level Coordination
Height difference control between the grating top and the road surface. For gratings installed on roadways, the top surface should be flush with or slightly lower than the road surface, with the difference not exceeding 3mm. For gratings installed on sidewalks or plazas, the top surface may be flush with the pavement or 1-2mm lower to facilitate drainage. The grating top surface must not be higher than the road surface.
Level coordination along the slope direction. The slope of the grating's top surface should align with the designed road slope, ensuring there are no reverse slopes or areas where water can pool. In the direction of drainage, the inlet side of the grating should be slightly lower than the road surface to facilitate the smooth entry of rainwater. When multiple gratings are installed in succession, the height difference between adjacent frame tops should not exceed 2mm.
Height during asphalt pavement construction. When installing gratings after asphalt paving, height mismatch issues often occur. Temporary covers should be installed or frame positions reserved before asphalt paving, with gratings installed after the road surface is formed. If post-installation is adopted, the frame top should be set 10-15mm below the designed asphalt surface elevation to allow for thickness adjustment space after compaction. Protective measures should be taken at grating positions during asphalt paving and rolling to prevent the asphalt mixture from entering the frame cavity.
III. Common Issues and Preventive Measures
Frame sinking is mainly caused by inadequate foundation compaction. Concrete foundation supports should be cast before installation to ensure design strength is achieved. Grating looseness and abnormal noise are usually due to levelness deviation or insufficient anchoring. Levelness should be strictly controlled and anchor points installed as per specifications. A grating higher than the road surface indicates level control error. Height should be rechecked point by point after installation, with allowance for paving. Damage around the frame is mainly caused by insufficient concrete strength or inadequate curing. Concrete of qualified grade should be used, and sufficient curing time should be ensured. Water pooling and poor drainage are often caused by improper level coordination along the slope direction. The grating top height should be adjusted according to the road slope to ensure smooth drainage.
IV. Installation Acceptance Checklist
The following items are recommended for key acceptance: concrete strength and flatness of the frame foundation; location, quantity, and connection reliability of anchor points; levelness and bidirectional height deviation of the frame top; clearance between grating and frame; and ease of grating opening.
V. Conclusion
The frame fixing and road level coordination of gully gratings are critical to drainage efficiency, traffic safety, and the service life of the facility. It is recommended that construction parties develop a detailed level control plan before installation, conduct point-by-point rechecks during installation, and perform acceptance checks in accordance with standards upon completion to ensure the long-term stable operation of the system.
For further information on our company's Gully Grating product specifications and technical support, please get in touch with the technical department to request relevant documentation.










